Annual Development Update: March 2022

  • News

Here We Grow Again!

Residential Development in Ward 1

Essex Town Centre 154 Singles, Semis, Towns: Phase 1 & 5 under construction Rush Drain Relocation & SWM Pond under construction. Servicing Drawings for Phases 2, 3, 4 under review.

Phase 3 Woodview Estates, 51 Singles: SWM Plan approved ECA Application under review Public Meeting to Consider Redline Amendment Required

Gianni Estates 86 Singles, Apartment Units: Tied to Hanlan Street Extension Pre-submission Stage

80 Maidstone 44 Townhome Units: Pre-consultation Stage

Jakana Subdivision 62 Singles: Full build-out achieved services and infrastructure assumed but not accepted

Townsview Subdivision 66 Singles: Full build-out achieved. Services and infrastructure assumed but not accepted

Industrial/Commercial in Ward 1

Liftow Toyota: Industrial/Construction vehicle sales dealership on South Talbot Road
• Under construction

Sturgeon Woods RV: Trailer Sales & Self-Storage Lot 2-phased RV Camper and Trailer
Sales Lot and Self-Storage Lot to be constructed on South Talbot Road
• Zoning By-law Amendment approved, Stormwater and Servicing Studies under review
• Site Plan Control Approval required

Essex Home Hardware: Relocation of Home Hardware in Essex Centre to Maidstone Avenue
• Site Plan Control application and associated studies under review

Hwy 3 Industrial Park: Preliminary discussions with a developer to subdivide vacant industrial land south of Highway 3 into 6-8 lots
• Pre-consultation with Town and regulatory agencies was held
• Planning applications have yet to be submitted

Dahl House: Renovation of former Dahl House for
ground floor retail/restaurant and second floor apartment units
• Under construction

Residential Development in Harrow

Dalla Bona Subdivision (Phase 1) 25 Singles – Planning approvals in place. Construction of Services and Roads ongoing. Holding restriction still in place.

Dalla Bona Subdivision (Phase 2) 12 single, semi, townhome dwelling blocks– Draft plan approved. Require clearance letters from ERCA and Town of Essex.

Dalla Bona Subdivision (Phase 3) 74 single and semi dwellings– Requires draft plan approval. Awaiting submission of servicing studies.

Parkland Woods 72 Singles, Semis– Phase 1, Registered Plan of Subdivision Phase 2, Draft Plan Approved, awaiting final approval.

Sunset Gardens (Phase 2) 60 Singles– Awaiting approval of servicing studies. Draft Plan Application to follow.

Industrial/Commercial in Ward 4

Boudreau Development
• Mixed use commercial plaza, two-storey office building, warehouse, repair garage, restaurant
for Phase 1 and 2
• Zoning Bylaw amendment for restaurant approved.
• Site plan control application for development received.
• Servicing studies in review stage.

Residential Development in Ward 2

Masaccio Drive 29 Singles – Registered Plan of Subdivision. Updated SWM Plan under review to
facilitate construction.

Ducharme Lane 22 Singles – Servicing Studies under review. Draft Plan Approval Required.

Parnell Street Apartments 116 unit Apartment Units– (Phase 1) 26 Townhome Dwelling Units
(Phase 2) SPC application submitted and under review.

Ingratta Subdivision 129 Singles – Pre-consultation with Town and regulatory agencies was held
Rezoning Required. Rezoning and Draft Plan of Subdivision only permitted to proceed if servicing allocation is available.

Residential Development in Ward 3

Colchester Bay 488 Singles, Semis, Towns, Apartment Units
• Pre-consultation with Town and regulatory agencies
was held
• Public Open House to be scheduled
• Draft Plan application to be submitted following
completion of various studies.

Colchester Heights (Ambassador Beach) 59 Singles • Pre-consultation with Town and regulatory agencies
was held
• Draft Plan application to be submitted following
completion of various studies.

Lypps Beach 100 Singles • Pre-consultation with Town and regulatory agencies was held
• Draft Plan application to be submitted following
completion of various studies.

Wellesley Drive Subdivision 42 Singles • Lots on Registered Plan of Subdivision Development Agreement to be entered into following completion of studies.

Erie Shores (Levergood) 96 Singles, Semis • Conceptual

Goodchild Beach / Erie Blue Road • Conceptual

Industrial/Commercial Ward 3

Upper Canada Growers Greenhouse Expansion and Ancillary Dwellings
• Rezoning application to add ancillary
dwellings ongoing
• New warehouse and greenhouse
applications to be processed under SPC.

Bell Road Greenhouse Construction of a 1.8 acre greenhouse
• SPC application submitted and under
review.

The Grove Motor Inn Construction of a 2 storey motel and cafe
• Building permit applications under
review.

Full Report click here:

https://townofessex-pub.escribemeetings.com/filestream.ashx?DocumentId=7054

Tune in Monday March 7th, 2022 to our YouTube channel to hear more details!